T1 - An additional layer of protection through superalarms with diagnosis capability
AU - Vásquez-Capacho, John William
AU - Perez-Zuñiga, Gustavo
AU - Muñoz, Yecid
AU - Ospino, Adalberto
N1 - Publisher Copyright:
© 2020 Ecopetrol S.A.. All rights reserved.
PY - 2020/6
Y1 - 2020/6
N2 - An alarm management methodology can be proposed as a discrete event sequence recognition problem where time patterns are used to identify the process safe condition, especially in the start-up and shutdown stages. Industrial plants, particularly in the petrochemical, energy, and chemical sectors, require a combined approach of all the events that can result in a catastrophic accident. This document introduces a new layer of protection (super-alarm) for industrial processes based on a diagnostic stage. Alarms and actions of the standard operating procedure are considered discrete events involved in sequences, where the diagnostic stage corresponds to the recognition of a special situation when these sequences occur. This is meant to provide operators with pertinent information regarding the normal or abnormal situations induced by the flow of alarms. Chronicles Based Alarm Management (CBAM) is the methodology used to build the chronicles that will permit to generate the super-alarms furthermore, a case study of the petrochemical sector using CBAM is presented to build the chronicles of the normal startup, abnormal start-up, and normal shutdown scenarios. Finally, the scenario validation is performed for an abnormal start-up, showing how a super-alarm is generated.
AB - An alarm management methodology can be proposed as a discrete event sequence recognition problem where time patterns are used to identify the process safe condition, especially in the start-up and shutdown stages. Industrial plants, particularly in the petrochemical, energy, and chemical sectors, require a combined approach of all the events that can result in a catastrophic accident. This document introduces a new layer of protection (super-alarm) for industrial processes based on a diagnostic stage. Alarms and actions of the standard operating procedure are considered discrete events involved in sequences, where the diagnostic stage corresponds to the recognition of a special situation when these sequences occur. This is meant to provide operators with pertinent information regarding the normal or abnormal situations induced by the flow of alarms. Chronicles Based Alarm Management (CBAM) is the methodology used to build the chronicles that will permit to generate the super-alarms furthermore, a case study of the petrochemical sector using CBAM is presented to build the chronicles of the normal startup, abnormal start-up, and normal shutdown scenarios. Finally, the scenario validation is performed for an abnormal start-up, showing how a super-alarm is generated.
KW - Alarm management
KW - Diagnosis
KW - Protection layers
KW - Safe process
KW - Super-alarm
UR - http://www.scopus.com/inward/record.url?scp=85089568735&partnerID=8YFLogxK
U2 - 10.29047/01225383.168
DO - 10.29047/01225383.168
M3 - Artículo Científico
AN - SCOPUS:85089568735
SN - 0122-5383
VL - 10
SP - 45
EP - 65
JO - CTyF - Ciencia, Tecnologia y Futuro
JF - CTyF - Ciencia, Tecnologia y Futuro
IS - 1
ER -